1 |
|
RKI-Renovation of Kattampalli project Stage 1 in Chirakkal Panchayath (Mechanical Works) |
View Progress | View Photos | Sep 24 2022 | 430 | View Work | |||||||
2 |
|
Rebuild Kerala Initiative- Flood Damages 2018- Restoration Of Nunungar Bridge in Pampa Triveni |
View Progress | View Photos | Mar 26 2021 | 139 | View Work | |||||||
3 |
|
Re -Build Kerala Initiative- Flood Damages 2018- Restoration of Canal at Karikkottumoola Padasekharam and Rejuvenation works to Thalakulam (Arumpanachira) in Ayarkunnam Panchayath |
View Progress | View Photos | Jan 25 2021 | 135 | View Work | |||||||
4 |
|
RKI-Repair and Rehabilitation of Koottayi Regulator cum
Bridge across Tirur-Ponnani Puzha in Mangalam Grama
Panchayath in Malappuram District- CIVIL WORKS. |
View Progress | View Photos | Jun 25 2022 | 230 | View Work | |||||||
5 |
|
RKI - Restoration and protection works to the breached right bund of LBMC between ch 0/200km and ch 0/500km, under the Chalakudy River Diversion Scheme |
View Progress | View Photos | Jul 22 2022 | 564 | View Work | |||||||
6 |
|
RKI-Urgent protection work using contiguous piles to the eroded bank of Manimala River from Thombilpady to Mulaykkalpady near Neerettupuram NSS Karayogam in ward no 6 of Thalavady Grama Panchayath |
View Progress | View Photos | Jul 28 2021 | 100 | View Work | |||||||
7 |
|
Peechi Scheme - aqueduct - a permanent solution at
breached portion of Left bund main canal bund between
ch.19/600 Km and 20/650 Km |
View Progress | View Photos | Dec 17 2021 | 290 | View Work | |||||||
8 |
|
Rebuild Kerala-Repair works of koodapuzha check dam in Chalakudy river -2019-20 |
View Progress | View Photos | Oct 15 2021 | 100 | View Work | |||||||
9 |
|
Rectification Works of Damaged Side Protection Wall at Chamravattom Regulator cum Bridge.(Retaining wall) |
View Progress | View Photos | Jul 14 2022 | 150 | View Work | |||||||
10 |
|
Chimoni Irrigation Project- Flood Damages -
Urgent rectification works to the damaged apron
on the downstream of stilling Basin in Chimoni
river |
View Progress | View Photos | Sep 26 2021 | 173 | View Work | |||||||
11 |
|
Replacement of 8 Nos.of MS shutters, Hoisting bridge and Hoisting Mechanism of Pozhikkara Regulator cum bridge in Kollam District-Mechanical works. |
View Progress | View Photos | Nov 09 2022 | 185.1 | View Work | |||||||
12 |
|
Flood damages- Rectification works at Kottenkottuvalavu Regulator for the year 2018-19 |
View Progress | View Photos | Oct 01 2021 | 75 | View Work | |||||||
13 |
|
Flood Damages - Rectification works at Illikkal Regulator
for the year 2018-19 |
View Progress | View Photos | Oct 01 2021 | 75 | View Work | |||||||
14 |
|
Flood 2018 -Renovation of shutters and hoisting
mechanism of Thrikkur regulator (Mechanical works) |
View Progress | View Photos | Mar 28 2021 | 108 | View Work | |||||||
15 |
|
RKI Maintenanace of storage weir across Manimala river near Moongani in Vellavoor Panchayath |
View Progress | View Photos | Oct 10 2021 | 50 | View Work | |||||||
16 |
|
Flood-2018-Renovation of Shutters and hoisting
Mechanism of Manjamkuzhy regulator (Mechanical
Works) |
View Progress | View Photos | Not updated | 359 | View Work | |||||||
17 |
|
PyIP-RKI-Restoration of damaged maincanal and UT near Ch.12/325km at Kara in Mattannur Muncipality |
View Progress | View Photos | Nov 06 2021 | 500 | View Work | |||||||
18 |
|
RKI - 2019 Improvements to Sellyampara Pond near sellyampara city in ward no.13 of Vellathuval
Panchayath. |
View Progress | View Photos | Mar 25 2021 | 15 | View Work | |||||||
19 |
|
Rebuild kerala Renovation of Kuppannur chal in
Kulanada Panchayath in Aranmula Constituency |
View Progress | View Photos | Jun 30 2021 | 218 | View Work | |||||||
20 |
|
Flood Damages 2018. Restoration of Sreeramapadam VCB across Pampa River in Pampa Thriveni. |
View Progress | View Photos | Dec 12 2020 | 19.88 | View Work | |||||||
21 |
|
RKI-Rectification of the eroded left bank of Kaliyar river
U/S of Paruthappuzha check dam cum tractor passage in
ward No.2 of Kodikkulam Panchayath. |
View Progress | View Photos | Nov 11 2021 | 23.5 | View Work | |||||||
22 |
|
Rebuild Kerala Initiative-Flood damages 2018 Restoration of a storage weir at Vattakavu(Urava) Noorumala bhagam in ward no.4 of Kadanad Panchayath |
View Progress | View Photos | Jan 29 2021 | 100 | View Work |