Irrigation Department

e-Monit - Work Monitoring System


Chief Engineer AS Issued On Going Not Started work Phy Completed Expenditure(in Lakhs)
Spill Over Current FY
CE-I&A 457 116 90 251 2708.17 8.17
CE PROJECT-I 54 5 10 39 0.00 0.00
CE PROJECT-II 138 16 20 102 285.06 0.00
CE IDRB 1 0 1 0 0.00 0.00
CE KP&INLAND 36 5 21 10 0.00 0.00
CE Mechanical 55 3 44 8 20.93 0.00
Total 741 145 186 410 3014.17 8.17

IRRIGATION & ADMINISTARTION
Total AS
457
Total TS
457
Tendered
375
Agreed
367
Physically Completed
251
PROJECT - I
Total AS
54
Total TS
54
Tendered
44
Agreed
44
Physically Completed
39
PROJECT - II
Total AS
138
Total TS
138
Tendered
119
Agreed
118
Physically Completed
102
IDRB
Total AS
1
Total TS
1
Tendered
1
Agreed
0
Physically Completed
0
KP & INLAND
Total AS
36
Total TS
36
Tendered
16
Agreed
15
Physically Completed
10
MECHANICAL
Total AS
55
Total TS
55
Tendered
12
Agreed
11
Physically Completed
8