e-Monit - Work Monitoring System


Chief Engineer AS Issued On Going Not Started work Phy Completed Expenditure(in Lakhs)
Spill Over Current FY
CE-I&A 31 9 1 21 18220.56 1.12
CE PROJECT-I 2 1 0 1 890.08 0.00
CE PROJECT-II 5 2 2 1 0.00 0.00
CE IDRB 1 1 0 0 0.00 0.00
CE KP&INLAND 0 0 0 0 0.00 0.00
CE Mechanical 3 2 0 1 93.10 0.00
Total 42 15 3 24 19203.74 1.12

IRRIGATION & ADMINISTARTION
Total AS
31
Total TS
31
Tendered
30
Agreed
30
Physically Completed
21
PROJECT - I
Total AS
2
Total TS
2
Tendered
2
Agreed
2
Physically Completed
1
PROJECT - II
Total AS
5
Total TS
5
Tendered
3
Agreed
3
Physically Completed
1
IDRB
Total AS
1
Total TS
1
Tendered
1
Agreed
1
Physically Completed
0
KP & INLAND
Total AS
0
Total TS
0
Tendered
0
Agreed
0
Physically Completed
0
MECHANICAL
Total AS
3
Total TS
3
Tendered
3
Agreed
3
Physically Completed
1