Irrigation Department
e-Monit - Work Monitoring System
NON PLAN WORKS :2023-24
Chief Engineer | AS Issued | On Going | Not Started work | Phy Completed | Expenditure(in Lakhs) | |
---|---|---|---|---|---|---|
Spill Over | Current FY | |||||
CE-I&A | 877 | 464 | 226 | 187 | 5883.73 | 164.05 |
CE PROJECT-I | 33 | 24 | 5 | 4 | 30.81 | 0.00 |
CE PROJECT-II | 273 | 155 | 58 | 60 | 796.70 | 81.22 |
CE IDRB | 57 | 49 | 7 | 1 | 257.46 | 0.00 |
CE KP&INLAND | 37 | 17 | 12 | 2 | 27.85 | 13.26 |
CE Mechanical | 6 | 3 | 2 | 1 | 24.87 | 0.00 |
Total | 1283 | 712 | 310 | 255 | 7021.42 | 258.52 |
IRRIGATION & ADMINISTARTION
Total AS
877
Total TS
787
Tendered
706
Agreed
651
Physically Completed
187
PROJECT - I
Total AS
33
Total TS
28
Tendered
28
Agreed
28
Physically Completed
4
PROJECT - II
Total AS
273
Total TS
225
Tendered
221
Agreed
215
Physically Completed
60
IDRB
Total AS
57
Total TS
53
Tendered
52
Agreed
50
Physically Completed
1
KP & INLAND
Total AS
37
Total TS
20
Tendered
19
Agreed
19
Physically Completed
2
MECHANICAL
Total AS
6
Total TS
4
Tendered
4
Agreed
4
Physically Completed
1