CHIEF ENGINEER WISE ABSTRACT :2024-25
Type | Total Work |
AS Amount (in Lakhs) |
On Going |
Phy Compl eted |
Expen diture (in Lakhs) |
Not Started work |
---|---|---|---|---|---|---|
I&A | 4665 | 378886.06 | 1267 | 2519 | 17584.74 | 876 |
PROJECT II | 5004 | 168902.52 | 753 | 2814 | 9000.28 | 1412 |
IDRB | 883 | 120116.74 | 181 | 193 | 679.49 | 498 |
PROJECT I | 3600 | 343397.98 | 538 | 1775 | 6348.68 | 1264 |
KP & INLAND | 1092 | 99270.10 | 223 | 531 | 4510.61 | 324 |
Mechanical | 161 | 9381.95 | 18 | 78 | 431.68 | 65 |
Total | 15405 | 1119955.34 | 2980 | 7910 | 38555.48 | 4439 |