Irrigation Department
e-Monit - Work Monitoring System
CHIEF ENGINEER WISE ABSTRACT :2022-23
Type | Total Work |
AS Amount (in Lakhs) |
On Going |
Phy Compl eted |
Expen diture (in Lakhs) |
Not Started work |
---|---|---|---|---|---|---|
I&A | 5219 | 410881.04 | 1153 | 3382 | 35891.66 | 680 |
PROJECT II | 4881 | 169617.35 | 547 | 3094 | 10474.98 | 1216 |
IDRB | 898 | 120057.04 | 129 | 280 | 1020.01 | 477 |
PROJECT I | 3276 | 303191.81 | 507 | 1812 | 6440.15 | 934 |
KP & INLAND | 1156 | 86252.80 | 220 | 609 | 5094.11 | 312 |
Mechanical | 144 | 9222.00 | 12 | 73 | 502.16 | 59 |
Total | 15574 | 1099222.05 | 2568 | 9250 | 59423.08 | 3678 |