Irrigation Department

e-Monit - Work Monitoring System


Chief Engineer AS Issued On Going Not Started work Phy Completed Expenditure(in Lakhs)
Spill Over Current FY
CE-I&A 829 285 98 446 9757.81 1318.02
CE PROJECT-I 90 17 45 28 35.47 4.17
CE PROJECT-II 475 165 92 217 1112.78 323.25
CE IDRB 61 23 1 37 43.34 88.48
CE KP&INLAND 18 4 4 6 76.62 38.17
CE Mechanical 15 2 1 12 31.78 10.19
Total 1488 496 241 746 11057.80 1782.28

IRRIGATION & ADMINISTARTION
Total AS
829
Total TS
777
Tendered
753
Agreed
731
Physically Completed
446
PROJECT - I
Total AS
90
Total TS
45
Tendered
45
Agreed
45
Physically Completed
28
PROJECT - II
Total AS
475
Total TS
402
Tendered
391
Agreed
382
Physically Completed
217
IDRB
Total AS
61
Total TS
61
Tendered
60
Agreed
60
Physically Completed
37
KP & INLAND
Total AS
18
Total TS
11
Tendered
10
Agreed
10
Physically Completed
6
MECHANICAL
Total AS
15
Total TS
14
Tendered
14
Agreed
14
Physically Completed
12