Irrigation Department
e-Monit - Work Monitoring System
NON PLAN WORKS :2022-23
Chief Engineer | AS Issued | On Going | Not Started work | Phy Completed | Expenditure(in Lakhs) | |
---|---|---|---|---|---|---|
Spill Over | Current FY | |||||
CE-I&A | 829 | 285 | 98 | 446 | 9757.81 | 1318.02 |
CE PROJECT-I | 90 | 17 | 45 | 28 | 35.47 | 4.17 |
CE PROJECT-II | 475 | 165 | 92 | 217 | 1112.78 | 323.25 |
CE IDRB | 61 | 23 | 1 | 37 | 43.34 | 88.48 |
CE KP&INLAND | 18 | 4 | 4 | 6 | 76.62 | 38.17 |
CE Mechanical | 15 | 2 | 1 | 12 | 31.78 | 10.19 |
Total | 1488 | 496 | 241 | 746 | 11057.80 | 1782.28 |
IRRIGATION & ADMINISTARTION
Total AS
829
Total TS
777
Tendered
753
Agreed
731
Physically Completed
446
PROJECT - I
Total AS
90
Total TS
45
Tendered
45
Agreed
45
Physically Completed
28
PROJECT - II
Total AS
475
Total TS
402
Tendered
391
Agreed
382
Physically Completed
217
IDRB
Total AS
61
Total TS
61
Tendered
60
Agreed
60
Physically Completed
37
KP & INLAND
Total AS
18
Total TS
11
Tendered
10
Agreed
10
Physically Completed
6
MECHANICAL
Total AS
15
Total TS
14
Tendered
14
Agreed
14
Physically Completed
12