e-Monit - Work Monitoring System
PLAN WORKS PROGRESS - 2022-23 - CURRENT FINANCIAL YEAR
Chief Engineer | AS Issued | On Going | Not Started work | Phy Completed | Expenditure(in Lakhs) | |
---|---|---|---|---|---|---|
Spill Over | Current FY | |||||
CE-I&A | 223 | 125 | 61 | 37 | 21416.84 | 0.00 |
CE PROJECT-I | 119 | 31 | 76 | 12 | 609.49 | 0.00 |
CE PROJECT-II | 173 | 44 | 69 | 60 | 1099.14 | 0.68 |
CE IDRB | 97 | 33 | 24 | 40 | 146.98 | 8.30 |
CE KP&INLAND | 123 | 38 | 65 | 20 | 4883.95 | 0.00 |
CE Mechanical | 4 | 1 | 1 | 2 | 0.00 | 0.00 |
Total | 739 | 272 | 296 | 171 | 28156.40 | 8.98 |
IRRIGATION & ADMINISTARTION
Total AS
223
Total TS
177
Tendered
168
Agreed
162
Physically Completed
37
PROJECT - I
Total AS
119
Total TS
47
Tendered
44
Agreed
43
Physically Completed
12
PROJECT - II
Total AS
173
Total TS
113
Tendered
106
Agreed
104
Physically Completed
60
IDRB
Total AS
97
Total TS
87
Tendered
79
Agreed
73
Physically Completed
40
KP & INLAND
Total AS
123
Total TS
64
Tendered
60
Agreed
58
Physically Completed
20
MECHANICAL
Total AS
4
Total TS
3
Tendered
3
Agreed
3
Physically Completed
2